Ref. Ares(2020)7898139 - 23/12/2020 -     Ref. Ares(2020)3490394 • 02/07/2020 Electronic Access to European Commission Documents Project Steering Committee meeting 18/06/2020
1

Agenda 1 _ Status 2. Budget 3 _ Planning 4. AOB / Q&A - - ' f_ European Commission I
2

Status Project Doing • Analysis of public portal     • Finishing analysis of change   • Analysis of public portal • First development contracts &   requests for request             search page and documentation (analysis,        management system                RegDoc/Com transition page architecture & development    • Evaluating Al proof-of-concept • First development releases & platform)                       based on deep learning           testing (navigation, • First internal development    • Drafting architecture overview   dashboards, access releases (integration to HRS,   document (July ITCB)             management, registration & CNS & UMC)                    • Drafting IT security plan        attribution of initial application) • Hosting infrastructure        • Analysing migration scenarios  • Procedure for the next outsourced development • Reviewing DG COMM contract (finish implementation comments on the public portal of request management • Checking support, training and   system) documentation requirements • Contract for the development with SG EU POLICYMAKING of the public portal HUB European Commission I
3

Status Compass Corporate & Al study • Compass Corporate • Steering Board has approved the postponement of the integration until the move to production and stabilisation of EASE • Architecture is designed around the use of Compass Corporate to facilitate future reintegration • Cost estimates for future integration with CC & MyWorkplace: 90 KEUR •  Recommendation: plan for 2022 to prioritise rollout and acceptance in 2021 • Study on artificial intelligence (Al) • DIGIT has made a new version of their deep learning proof-of-concept (PoC) available to us for testing until the end of July • If the results are conclusive the follow-up would be to initiate a Memorandum of Understanding to industrialise the Poe so that it could be integrated in EASE •  Recommendation: do this in 2021+ after the move to production European Commission I
4

Status ColdFusion, migration & archiving • ColdFusion • The RegDoc form that is enabling users to request access to documents will remain until the EASE portal is deployed • This form will be migrated to Cold Fusion 2018 for the interim period between the phase-out of ColdFusion 11 (31/03/2021) and the move to producfion of EASE (April-May 2021) • Data migration & archiving • Migration scenario: fully migrate the content of GestDem to EASE while respecting the retention policy •  Initial applications: delete 5 years after closure •  Confirmatory applications: archive 5 years after closure • Propose to postpone long-term archiving (HPS) to 2022 and to base it on the Ares & migrated EASE data European Commission I
5

Status Change requests & security plan • Change requests (25+ open, 70+ in total) • Overhead •  The rate of growth of the CRs is not manageable, they require: analysis, prioritisation, estimates and plann ing prior to implementation •  Deloitte no longer have the capacity to integrate them •  Some of them can be handled internally at analysis or development time, but internal capacity is also limited • Need to set a scope baseline for the first version: freeze non-essential CRs (< HIGH priority) and wait for testing and production • Security plan • Identification and valuation of primary assets (main components and data entities) is ongoing, due for review and approval for end of June European Commission I
6

Budget 2020 H1 2020 H1                       Source Amount (K EUR) Requested                                       915 2 EASE development         ISA (2019)             190 2 EASE development         ISA (2020)             550 EASE development            RegPub              100 EASE security plan           Studies              75 Consumed                                        490 Portal analysis contract                        270 lntramuros resources                            220 Remaining                                       425 ~ ~ European Commission I -
7

Budget 2020 H2 2020 H2                                                                Source Amount (K EUR) Remaining                                                                                425 EASE extramuros contract                                             2 ISA (2020)                65 - Development of the public portal EASE extramuros contract - Confirmatory & search development                               2 ISA (2020)              100 - Post-production care (support & change requests) - Portal development contingency 2 EASE usability testing                                           ISA (2020)                20 EASE intramuros - Internal analysis (portal search & RegDoc/Com transition)     2 ISA (2020) & - Internal development (integration & migration CF 2018)                              240 Studies - Data migration - Security plan ~ ~ European Commission I -
8

Planning Request management system releases Release 1 (September) European Commission I
9

Planning                                                                                                 Milestones •    RMS Production Roadmap                                                                                                       PP Production ¼'. Contract required Year                                  2020                                                                2021 Q1      Q2               Q3                    Q4                         Q1                   Q2 • Analysis • Development                   It • Acceptance                                                      ACC1                       ACC2             ACC3 Public portal (PP) • Analysis • Development                                            1//////ffi'/////hW////AV////MV~n'/2 • Testing                                                                                    ACC1             ACC2 Migration & security (MIG & SP) • Migration                             Analysis                                Development                  Testing • Security                                           Secunty plan                  Security tests (RMS) Security tests (PP) Business implementation (Bl) • Training                                    lrntIatIon               Preparation I I European Commission